June 2018 | Corporate

Construction Update Q2/2018

Latest progress of Chao Phraya Estate’s newest luxury collection.


Despite the downpour rain in the past few months, the external façade installation of Four Seasons Private Residences Bangkok at Chao Phraya River has progressed to level 65 which went according to plan. The installation is expected to be completed in the next quarter. The interior design works in the Reception Lobby, River Lounge, and Amenities Deck is expected to be completed in Q4/2018.

The construction of Four Seasons Hotel Bangkok at Chao Phraya River has reached the 13th floor, whilst the external façade installation has progressed to level 4. Currently, the team is commencing interior works for guestroom and the public area with all the main equipment already on site.

Meanwhile, Capella Bangkok has successfully completed architectural work, interior guestroom and public area works is moving forward smoothly according to plan and will be ready to open in Q4/2018. With the completion of Four Seasons Private Residences and Capella Bangkok, Chao Phraya Estate will be the spectacular site by the end of the year.



May 2017 | Lifestyle

Into the Light

Singapore-based lighting specialist, Project Lighting Design (PLD) brings the best out of iconic buildings and stunning interior spaces at Chao Phraya Estate.

March 2017 | Corporate

Capella Bangkok Top-Off Ceremony at Chao Phraya Estate

Chao Phraya Estate welcomes all-suite Capella Bangkok to its illustrious neighbourhood.

September 2018 | Corporate

Clean up the World 2018

CGD goes green with community clean-up along the river of kings.